Deadlines for special transport
Topic | Examples | Deadline |
---|---|---|
Events | Large-scale orders: shuttle transport for major events such as Airpower and the Hahnenkamm-Rennen ski race | 2 months |
Measurement and test runs | Large-scale order: measurement runs in excess of local permitted speed | 2 months |
New traffic | Requiring significant processing work for ÖBB-Infrastruktur AG: runs outside of route opening times, circulation-related transport or shunting requirements | 1 month |
Other complex orders and scheduled traffic | Training runs, special tour trains, "nostalgic" runs, construction site logistics, transportation of gravel, coal, ore and sugar beets, transformer transports | 2 weeks |
Special trains with exceptional consignments | Specific conditions of carriage | 5 days |