All about the building

Wolfurt station is being modernised in several phases

Modernization of the Wolfurt Train Station<br/>

Step by step towards a modern station

The modernisation of Wolfurt railway station is taking place in several construction phases whilst rail services continue to operate. This means that passengers can continue to use the station during the building works. Step by step, a modern transport hub is taking shape that meets the requirements for accessibility, comfort and better connections between different modes of transport. The forecourt, complete with Bike & Ride and Park & Ride facilities, is due to be completed in autumn 2026.

Facts & Figures

    • Investment in the station: around 21 million euros
    • Total project cost, including surrounding area improvements: around 49 million euros
    • Platform length: 220 metres
    • Platform height: 55 centimetres for barrier-free access
    • 3 new lifts
    • 244 Bike & Ride spaces
    • 68 lockable bike boxes
    • 20 covered moped spaces
    • 16 Park & Ride spaces
    • Over 3,000 metres of renewed track
    •  Around 80 m² art installation ‘What Moves Us’
    •  118 contributions from residents as the basis for the art project
    •  Construction period for the transport hub: 2024 to 2025
    •  Completion of the forecourt: 2026

More than just a station refurbishment

The project involves far more than simply refurbishing the platforms. As well as modernising the pedestrian underpass and installing lifts, the cycle parking facilities have been expanded, new cycle lockers have been installed and the forecourt has been redesigned. At the same time, ÖBB is investing in the renewal of tracks, points and technical infrastructure in the station area.

Project partners: ÖBB-Infrastruktur AG, the State of Vorarlberg, the market town of Wolfurt.